Construction Progress…
April 15, 2026
Preparing to begin the new sheet pile wall, near the new boat ramp.
West pavilion building being constructed.
Scaffolding in place to begin framing marina building.
West and south pavilion framework completed, next up the concrete slab and roof.
Notice the concrete gangway landings, so local seafood can be unloaded and sold here soon!
March 12, 2026
First components of south pavilion building being installed.
Drone photo showing location of new sheet piling wall.
South pavilion building construction underway.
Storm drainage materials being unloaded.
February 12, 2026
Overall project site view from Flythecoast.com.
Rock revetment being installed on southside of shoreline.
Foundations for future open air market and pavilion.
Pipe piling being installed.
January 16, 2026
Layout for future open-air market pavilion
Driving piling for future open-air market pavilion
New drainage boxes onsite, ready to be installed
Piling Installation for Future Event Stage
December 23, 2025
Piling for future marina building.
Piling installation for future pavilion building.
November 12, 2025
Currrent Site Conditions
Piling Test.
October 13, 2025
Wood Piling and Bulkhead Removal.
Boat Launch Removal.
September 8, 2025
A Ground-breaking Ceremony was held September 8, 2025. Demolition activities will begin soon.
Current Project Site.
Soil work in area of future parking area .
Site Grading Underway.
Sitework and Rock Revetment.
Casino boats have been removed from the area, and the current demolition status is shown.
Concrete Pier Removal and Material stockpiled.