Construction Progress…

March 12, 2026

First components of south pavilion building being installed.

Drone photo showing location of new sheet piling wall.

South pavilion building construction underway.

Storm drainage materials being unloaded.


February 12, 2026

Overall project site view from Flythecoast.com.

Rock revetment being installed on southside of shoreline.

Foundations for future open air market and pavilion.

Pipe piling being installed.


January 16, 2026

Layout for future open-air market pavilion

Driving piling for future open-air market pavilion

New drainage boxes onsite, ready to be installed

Piling Installation for Future Event Stage


December 23, 2025

Piling for future marina building.

Piling installation for future pavilion  building.


November 12, 2025

Currrent Site Conditions

Piling Test.


October 13, 2025

Wood Piling and Bulkhead Removal.

Boat Launch Removal.

September 8, 2025

A Ground-breaking Ceremony was held September 8, 2025. Demolition activities will begin soon.

Current Project Site.

Soil work in area of future parking area  .

Site Grading Underway.

Sitework and Rock Revetment.

Casino boats have been removed from the area, and the current demolition status is shown.

Concrete Pier Removal and Material stockpiled.


Ground-breaking ceremony was held on September 8, 2025.  Preparation for demolition will begin right away, followed by full demolition activities for the first month of the project.

December 23, 2025

Piling for future marina building.

Piling installation for future pavilion  building.


November 12, 2025

Currrent Site Conditions

Piling Test.


October 13, 2025

Wood Piling and Bulkhead Removal.

Boat Launch Removal.

September 8, 2025

A Ground-breaking Ceremony was held September 8, 2025. Demolition activities will begin soon.

Current Project Site.

Soil work in area of future parking area  .

Site Grading Underway.

Sitework and Rock Revetment.

Casino boats have been removed from the area, and the current demolition status is shown.

Concrete Pier Removal and Material stockpiled.


Ground-breaking ceremony was held on September 8, 2025.  Preparation for demolition will begin right away, followed by full demolition activities for the first month of the project.