Construction Progress…

June 15, 2026

Marina building taking shape.

New sidewalk being poured between the marina building and pavilions.

Pavillion slab being poured.

New sidewalk, curb and parking lot work on the south side of the project.

New pavilions (waiting on roofs). Who’s ready to have an event under these pavilions?

New sidewalk being poured on the south side of the project.

May 20, 2026

Installation of sheet piling wall at future boat ramp area.

Placement of rip rap along the shoreline.

Preparations for the concrete slab at one of the two the new pavilions.

New sidewalk along the shoreline, with new pavilions in the background.


April 15, 2026

Preparing to begin the new sheet pile wall, near the new boat ramp.


West pavilion building being constructed.

Scaffolding in place to begin framing marina building.

West and south pavilion framework completed, next up the concrete slab and roof.

Notice the concrete gangway landings, so local seafood can be unloaded and sold here soon!

March 12, 2026

First components of south pavilion building being installed.

Drone photo showing location of new sheet piling wall.

South pavilion building construction underway.

Storm drainage materials being unloaded.





February 12, 2026

Overall project site view from Flythecoast.com.

Rock revetment being installed on southside of shoreline.

Foundations for future open air market and pavilion.

Pipe piling being installed.


January 16, 2026

Layout for future open-air market pavilion

Driving piling for future open-air market pavilion

New drainage boxes onsite, ready to be installed

Piling Installation for Future Event Stage


December 23, 2025

Piling for future marina building.

Piling installation for future pavilion  building.


November 12, 2025

Currrent Site Conditions

Piling Test.


October 13, 2025

Wood Piling and Bulkhead Removal.

Boat Launch Removal.

September 8, 2025

A Ground-breaking Ceremony was held September 8, 2025. Demolition activities will begin soon.

Current Project Site.

Soil work in area of future parking area  .

Site Grading Underway.

Sitework and Rock Revetment.

Casino boats have been removed from the area, and the current demolition status is shown.

Concrete Pier Removal and Material stockpiled.


Ground-breaking ceremony was held on September 8, 2025.  Preparation for demolition will begin right away, followed by full demolition activities for the first month of the project.